Carrier 30HK User Manual
Reciprocating liquid chillers (60 hz)
Attention! The text in this document has been recognized automatically. To view the original document, you can use the "Original mode".
Number One
Airconditioning
Maker
Carrier Parkwav • Syracuse NY 13221
Reciprocating Liquid Chillers (60 Hz)
All 208/230-volt units have extended-voltage
compressor motors.
All units have suction-cutoff unloading
system.
CONTENTS
Page
• RIGGING
• PLACEMENT
Step 3 — Check Compressor Mounting
and Connections.................................................................. 3
• SERVICE ACCESS
Step 4 — Make Piping Connections ...................................... 3
• CONDENSER DESCRIPTION
• CONDENSER PIPING
• COOLER DESCRIPTION
• COOLER PIPING
Step
5
— Make Electrical Connections ..................................4
• ELECTRICAL BOX, CONTROL SECTION
• UNBALANCED 3-PHASE SUPPLY
VOLTAGE
• ELECTRICAL BOX, POWER SECTION
START-UP AND SERVICE.................................................. 6
Initial Check............................................................................ 6
Check Refrigerant Charge..................................................... 6
• LIQUID CHARGING METHOD
Check Oil Charge................................................................... 7
• TO ADD OIL
• TO REMOVE OIL
START-UP............................................................................ 7-10
Check Refrigerant Feed Components................................... 7
• THERMOSTATIC EXPANSION VALVE
• FILTER DRIER
• MOISTURE-LIQUID INDICATOR
• LIQUID-LINE SERVICE VALVE
• LIQUID-LINE SOLENOID VALVE
• PRESSURE RELIEF DEVICES
• CHECK VALVE
Check Compressor Protection Devices_
• CIRCUIT BREAKER
• MOTOR OVERTEMPERATURE
THERMOSTAT
• CRANKCASE HEATER
• TIME GUARD® CONTROL
• FOUR-FUNCTION TIMER
• OIL PRESSURE SAFETY
SWITCH (OPS)
Check Unit Safety Devices........................
• SAFETY THERMOSTAT
• HIGH-PRESSURE SWITCH
• LOW-PRESSURE SWITCH
Check Capacity Control System...............
10
DESCRIPTION
3-STEP TEMPERATURE
CONTROLLER
DESIGN SET POINT ADJUSTMENT
CYLINDER UNLOADING SYSTEM
Page
UNIT OPERATION...........................................................10-11
Control Power....................................................................... 10
Control Sequence.................................................................. 11
Unit Stoppage and Restart.................................................. 11
SERVICING COOLER..................................................... 11-13
Tube Plugging ....................................................................... 12
Retubing ................................................................................ 12
Tightening Cooler Head Bolts ............................................. 12
• GASKET PREPARATION
• BOLT TORQUES
• BOLT TIGHTENING SEQUENCE
TROUBLESHOOTING GUIDE....................................... 14,15
SAFETY CONSIDERATIONS
Installation, start-up and servicing of this
equipment can be hazardous due to system pres
sures,
electrical
components
and
equipment
location (roofs, elevated structures, etc.).
Only trained, qualified installers and service
mechanics should install, start-up and service
this equipment.
When working on the equipment, observe pre
cautions in the literature, tags, stickers and labels
attached to the equipment and any other safety
precautions that apply.
• Follow all safety codes.
• Wear safety glasses and work gloves.
• Use care in handling, rigging and setting bulky
equipment.
INSTALLATION
Step 1 — Inspect Shipment
Inspect unit for damage or missing parts. If dam
age is detected, or if shipment is incomplete, file a
claim immediately with the shipping company.
Step 2 — Rig and Place Unit
RIGGING
On each end of cooler, a steel loop is provided for
the preferred method of lifting unit.
Use spreader
bars to keep cables away from compressor enclo*-
sure and control box. If unit is to be moved by fork
truck, use the following methods:
1. From front or rear, lift under the cooler rails.
Unit can be either on or off skid.
2. When moving from ends,
leave unit on skid. Lift
from under skid.
© Carrier Corporation 1983