Wiring the SLC Servo Module 5-15

To operate the encoder, wire the encoder so that marker Z is true at
the same time that A and B channels are true. To wire the encoder for
consistent homing of the axis, do the following:

1. Obtain the encoder output timing diagram from the vendor’s

data sheets. A typical example is shown in Figure 5.12.

2. On the timing diagram, look at marker Z and its complement,

marker Z.

3. Determine which signal is low for most of the encoder

revolution and pulses high for the marker interval.

4. Wire the signal that was determined in Step 3 to CH Z.HI on the

termination panel.

5. Wire the other to CH Z.LO on the termination panel.

6. Look at channel B and its complement, channel B.

7. Wire CH B.HI on the termination panel to the signal that is high

for at least part of the marker interval. Depending on the
encoder manufacturer, it is possible that both channels meet this
requirement. If so, use either one.

8. Wire the complementary remaining phase to CH B.LO on the

termination panel.

9. Look at channel A and its complement channel A.

10. Wire the signal that is low for most of the encoder revolution

and pulses high for the marker interval to CH A.HI on the
termination panel.

11. Wire the complementary signal to CH A.LO on the termination

panel.

Typical Vendor Encoder Wiring

See your vendor’s encoder literature for the applicable timing
diagram.