Installation in tanks containing one liquid and foam

• Drill a pressure equalization hole in the stilling well above the maximum level.
• Deburr the hole.
• If the probe has a counterweight, make sure that there is enough space between the

counterweight and the wall of the stilling well.

Installation in tanks containing more than one liquid

• Drill a pressure equalization hole in the stilling well above the maximum level of the top liquid.
• Drill more holes along the length of the stilling well. Distance between holes ≥ 25 mm / 1¨

(depends on the minimum layer to be measured)

i

These holes help the liquids to move freely.

• Deburr the holes.
• If the probe has a counterweight, make sure that there is enough space between the

counterweight and the wall of the stilling well.

Floating roofs

If the device is for a tank with a floating roof, install it in a stilling well.

Figure 3-18: Installation recommendations for stilling wells

1 Stilling well in tanks containing one liquid
2 Stilling well in tanks containing more than one liquid
3 Air circulation hole
4 Maximum level of the liquid
5 Liquid circulation hole
6 Distance between holes ≥ 25 mm/1¨ (depends on the minimum layer to be measured)