Installation – KROHNE OPTIFLEX 1300C EN User Manual
Page 29
INSTALLATION
3
29
OPTIFLEX 1300 C
www.krohne.com
03/2014 - 4000172306 - HB OPTIFLEX 1300 R07 en
Installation in tanks containing one liquid and foam
• Drill a pressure equalization hole in the stilling well above the maximum level.
• Deburr the hole.
• If the probe has a counterweight, make sure that there is enough space between the
counterweight and the wall of the stilling well.
Installation in tanks containing more than one liquid
• Drill a pressure equalization hole in the stilling well above the maximum level of the top liquid.
• Drill more holes along the length of the stilling well. Distance between holes ≥ 25 mm / 1¨
(depends on the minimum layer to be measured)
i
These holes help the liquids to move freely.
• Deburr the holes.
• If the probe has a counterweight, make sure that there is enough space between the
counterweight and the wall of the stilling well.
Floating roofs
If the device is for a tank with a floating roof, install it in a stilling well.
Figure 3-18: Installation recommendations for stilling wells
1 Stilling well in tanks containing one liquid
2 Stilling well in tanks containing more than one liquid
3 Air circulation hole
4 Maximum level of the liquid
5 Liquid circulation hole
6 Distance between holes ≥ 25 mm/1¨ (depends on the minimum layer to be measured)