SMA SI 3.0-11 User Manual
Page 20
4 Starting and Stopping the System
SMA Solar Technology AG
20
SI30M-44M-60H-80H-BE-en-30
Operating Manual
4.5 Tripping the Emergency Disconnection of the System
Procedure:
• Press and hold the "Off" button on the Sunny Island until an
acoustic signal sounds.
☑ The inverter LED is off on all Sunny Island inverters.
4.6 Setting Time-Controlled Inverter Operation in Off-Grid Systems
Requirement:
☐ The Sunny Remote Control must be in user mode (see Section 5.3, page 27).
Procedure:
1. Select the Inverter display page on the Sunny Remote Control and press the
button.
☑ The Sunny Remote Control switches to the Inverter setting page.
2. Set the time-controlled inverter operation:
• Select the Start Date parameter and set it to the desired start date.
• Select the Start Time parameter and set it to the desired start time.
• Select the Run Time parameter and set it to the desired run time.
• Select the Repetition parameter and set it to the desired repetition cycle.
3. To activate time-controlled inverter operation, select the Timed Start parameter and set it to Enable.
☑ Time-controlled inverter operation is activated. If the Sunny Island has started automatically under time-control and
you stop the Sunny Island, time-controlled inverter operation is deactivated automatically.
Effects of an emergency disconnection
Emergency disconnection triggers the uncontrolled shutdown of the system and unsaved data is lost.
• Only use emergency disconnection to avoid danger or consequential damages.
Example: Parameter settings for time-controlled inverter operation
You want to operate the Sunny Island in inverter operation every Sunday from 10:00 a.m. to 6:00 p.m., starting on
Sunday, January 8, 2012. To do this, set the Sunny Island as follows:
• Str.Date: 08.01.2012
• Start Time: 10:00:00
• Run Time: 08:00:00
• Repetition: Weekly