Configuration prerequisites
Before scheduling an NQA test group, make sure:
z
Required test parameters corresponding to a test type have been configured;
z
For a test that needs the cooperation with the NQA server, configuration on the NQA server has
been completed.
Scheduling an NQA test group
Follow these steps to schedule an NQA test group:
To do…
Use the command…
Remarks
Enter system view
system-view
—
Schedule an NQA test group
nqa schedule admin-name operation-tag
start-time { hh:mm:ss [ yyyy/mm/dd ] | now }
lifetime { lifetime | forever }
Required
Configure the maximum number of
tests that the NQA client can
simultaneously perform
nqa agent max-concurrent number
Optional
2 by default.
z
After an NQA test group is scheduled, you cannot enter the test group view or test type view.
z
A started test group or a test group that has completed tests will not be influenced by the system
time change; only a test group that is waiting to perform tests will be influenced by the system
time change.
Displaying and Maintaining NQA
To do…
Use the command…
Remarks
Display history records of NQA
test operation information
display nqa history [ admin-name
operation-tag ]
Display the results of the last NQA
test
display nqa result [ admin-name
operation-tag ]
Display the statistics of a type of
NQA test
display nqa statistics [ admin-name
operation-tag ]
Display NQA server status
display nqa server status
Available in any view