Hardware Preparation and Installation

2.1

Unpacking and Inspecting the Blade

This section describes the procedure for packing and inspecting the blade.

Shipment Inspection

To inspect the shipment, perform the following steps.

1. Verify that you have received all items of your shipment:

ATCA-7370/ATCA-7370-S blade

A printed copy of Quick Start Guide

A printed copy of Safety Notes Summary

Any optional items ordered

2. Check for damage and report any damage or differences to the customer service.

3.

Remove the desiccant bag shipped together with the blade and dispose of it according to
your country’s legislation.

Damage of Circuits
Electrostatic discharge and incorrect blade installation and removal can damage circuits or
shorten its life.
Before touching the blade or electronic components, make sure that you are working in an
ESD-safe environment.

The blade is thoroughly inspected before shipment. If any damage occurred during
transportation or any items are missing, contact our customer service immediately.