Chapter 3: Robot Installation - HS
Ground bolt
and label
Figure 3-12. Cable Inlet Box, showing Ground Label
2. Install the M4 protective earth ground bolt, with toothed washer, through the cable inlet
box into the AIB/eAIB. See the preceding figure.
l
Ensure that the protective earth ground wire lug is under the toothed washer.
l
This bolt does not need Loctite.
l
Torque the bolt to 1.1 N·m (10 in-lb).
3. Attach the cable inlet box back cover with four M4 x 16 bolts.
l
Ensure that the gasket is seated between the cover and the cable inlet box.
l
Put one washer seal under each bolt head.
l
Use Loctite 222 in these bolt holes, not on the bolts themselves.
l
Torque bolts to 1.1 N·m (10 in-lb).