3 repacking for relocation – Adept s650HS Quattro User Manual
Page 45

Chapter 3: Robot Installation - HS
2. Lift off the cardboard sides.
Under the robot base, the ancillary items will be attached to the crate bottom. Refer to
the preceding figure.
Figure 3-3. L-Bracket Securing Robot to Shipping Crate
The robot base is held in place in the crate with L-brackets and machine bolts.
1. Place a protective pad over the AIB/eAIB to protect it from damage from tools during
the removal of the L-brackets.
2. Remove the three hex-head wood screws (0.25 in.) from each bracket.
Retain the wood screws and washers for possible future relocation.
3. Remove the M16 bolt and lock and flat washers from each bracket.
Retain the M16 bolts and lock and flat washers for possible future relocation.
NOTE: These are not the M16 bolts used for mounting the robot.
3.3 Repacking for Relocation
If the robot or other equipment needs to be relocated, reverse the steps in the installation
procedures that follow in this chapter. Reuse all original packing containers and materials and
follow all safety notes used for installation. Improper packaging for shipment will void your
warranty.
Adept Quattro User's Guide, Rev F
Page 45 of 196