Visual inspection, 7commissioning, 5 check protective equipment – Pilz PSENvip RL D P User Manual
Page 107: 2 visual inspection

Pilz GmbH & Co. KG, Felix-Wankel-Straße 2, 73760 Ostfildern, Germany
Telephone: +49 711 3409-0, Telefax: +49 711 3409-133, E-Mail: [email protected]
7-25
7.5
Check protective equipment
7
Commissioning
The test piece interrupts the advance measuring field. The press stroke
is stopped. The upper tool should not touch the test piece.
Once the press stroke has stopped, push the 15 mm high section of
the test piece beneath the upper tool.
The upper tool should not touch the test piece.
Function test using the 35 mm test piece
Start up the press.
Position the 35 mm high section of the test piece on top of the lower
tool.
Initiate a press stroke.
The test piece interrupts the advance measuring field. The press stroke
is stopped. The upper tool should not touch the test piece.
7.5.2
Visual inspection
Visual inspection
7-
Inbetriebnahme_Schutzeinrichtung_pruefen_Sichtpruefung
Check the following on the PSENvip transmitter and receiver
The condition of the installation and attachment
Any damage on the housing and lens
Electrical connections
Switch on the machine.
Check the messages on the display.