beautypg.com

SMA SI 3324 Installation User Manual

Page 98

background image

System Examples

SMA

Technologie AG

Page 98

SI3324/4248-14:SE2406

Installation Guide

The following parameters must be set:

No.

Parameter

Parameter value/unit

Parameter description

23-2

BatType
(see section 11.4)

refer to the data sheet
provided by the battery
manufacturer

The type of battery used in the system. To be
set when first commissioning the system (see
section 8.2 "Initialization" (Page 66)).

23-3

AmpHoursBat
(see section 11.4)

refer to the data sheet
provided by the battery
manufacturer

Battery capacity. To be set when first
commissioning the system (see section 8.2
"Initialization" (Page 66))
.

23-4

AmpdcBatMax
(see section 11.4)

refer to the data sheet
provided by the battery
manufacturer

Max. battery charging current. To be set
when first commissioning the system (see
section 8.2 "Initialization" (Page 66)).

24-2

AmpacGenMax

0.85 * max. grid current
fuse

Max. generator output current (see section
8.5.2 "Setting the Output Current Limit"
(Page 77))
.

24-8

GridConnected
(Stby)*

GridCharge (without
Sunny Boy inverter);
GridFeedPV (with Sunny
Boy inverter)

Operating mode of the Sunny Island 3324/
4248 when connected to the public grid (see
section 8.4 "Operating with the Public Grid"
(Page 72))
.

40-2

Autostart

On

The Sunny Island 3324/4248 can restart
automatically.

40-6

LoadShedding

Auto

Automatic control of the load shedding relay
by the Sunny Island 3324/4248

40-8

SunnyBoys

Yes

Set this parameter to Yes when Sunny Boy
inverters are connected to the system.

*

* depending on national requirements
MSD: see 21 "Glossary" (Page 153)