9.2
Switching On/Starting
Proceed as follows:
1.
Switch on the Sunny Island 3324/4248 by switching the DC circuit breaker to
the "ON" position.
2.
The Sunny Island 3324/4248 begins the
initialization phase (INIT), during which a
number of self-tests are performed to check
that there are no faults in the system.
3.
You must wait for this to finish.
4.
As soon as the initialization phase is finished,
the message "To start press
displayed.
5.
Now press
3324/4248 will start.
6.
A single beep will be heard. The green LED
on the control panel of the Sunny Island
3324/4248 will illuminate.
This step assumes that the Sunny Island 3324/4248 has been
checked for
• correct connections,
• voltages and
• polarities
and has already been commissioned by a qualified electrician.
If the inverter does not display the "To start press
displays a fault message instead, then this fault must be corrected before the
inverter can be put into operation. Use the information in section 18
"Troubleshooting/Problem Solving" (Page 143)
have been taken, switch off the Sunny Island 3324/4248, then wait for 30
seconds before beginning anew from point 1.
SMA SMA SMA SMA
To start
press