Set the parameters 23-2, 23-3 and 23-4, one after the other. The exact sequence is
described in section 8.2 "Initialization" (S. 66), points 8—21.

5.

Now set the battery type ("23-2 BatType"
parameter).

6.

Press the arrow key (↓) to access the
parameter for setting the battery capacity in
ampere hours ("23-3 AmpHoursBat"
parameter).

7.

Press the arrow key (↓) to reach the
parameter for setting the maximum battery
charging current ("23-4 AmpdcBatMax"
parameter) (see section 8.1 "Preparation"
(Page 63)
).

8.

Press to end the initialization process.

9.

The message "To start press " is
displayed. The Sunny Island 3324/4248 is
now ready to start.

Parameter information is also provided in section 17.2.2 "Adjustable System
Parameters" (Page 134)
.

BatType ‹23

VRLA

AmpHoursBat ‹23

100 Ah

AmpdcBatMax ‹23

10 A

To start