7.

Carefully press the new EPROM into the socket, with the angled corner at the
bottom left of the socket. The side of the component with the label must be
visible.

8.

Remove all tools from the Sunny Island 3324/4248.

9.

Close the housing cover once more (see section 6.2 "Installing the Cover"
(Page 56)
).

For the subsequent (re)start, the Sunny Island 3324/4248 requires a few seconds
longer than usual for the initialization process. Switch on the Sunny Island 3324/
4248 as described in section 8.2 "Initialization" (Page 66).

The following messages appear in the display:

• SMA Logo
• Updating DSP (the progress bar shows the progress of the update)
• Update complete
• SMA Logo
• To Init System Press

10. Check the parameter settings required for first commissioning (see section 8.2

"Initialization" (Page 66)) and set the correct values if necessary.

11. Press to leave the menu.

12. The Sunny Island 3324/4248 is ready for

operation. The message "To start press
" is displayed.

Once the Sunny Island 3324/4248 has been switched on again, the measuring
channels are recalibrated if necessary. Make sure that the AC input and AC
output terminals of the inverter are free of voltage. Once calibration has been
successfully completed, the message "Offscalib" appears in the display.