2 installation – Comtech EF Data SLM-5650A User Manual

Page 52

background image

SLM-5650A Satellite Modem

Revision 8

Installation

MN-SLM5650A

2–2

The equipment contains parts and assemblies sensitive to damage by Electrostatic

Discharge (ESD). Use ESD precautionary procedures when touching, removing, or

inserting PCBs.

Step Task

1

Keep all shipping materials for storage or reshipment.

2

Check the packing list to ensure the shipment is complete.

3

Inspect the equipment for any possible damage incurred during shipment.

Contact the carrier and Comtech EF Data immediately and submit a damage report if damage is evident to

the shipment.

4

Read the manual.

2.2 Installation

When installing the SLM-5650A into a rack enclosure (Figure 2-2):
PROPER GROUNDING PROTECTION IS REQUIRED. The equipment must be connected to

the protective earth connection at all times. It is therefore imperative that the unit is properly

grounded, using the ground stud provided on the unit rear panel, during installation,

configuration, and operation.
PROPER AIR VENTILATION IS REQUIRED. In a rack system where there is high heat

discharge, provide forced-air cooling with top- or bottom-mounted fans or blowers.
Make sure there is adequate clearance inside the enclosure, especially at the side for air

ventilation.
Air temperature inside the rack enclosure should

never

exceed 50°C (122°F).