Synchronize pe immediately, Switch region, Remove pe – HP Intelligent Management Center Licenses User Manual
Page 76: Synchronize pe immediately switch region remove pe
Parameters
•
Synchronization Status: Last synchronization status of a PE, including "Succeeded", "Failed",
"Synchronization is running", and "--". "--" means PE device synchronization status is unknown.
It may be caused by during PE synchronization stop MPLS VPN daemon process. In this case
please synchronize PE device manually.
Synchronize PE immediately
Operation procedure
Approach 1
Click the Service tab, click MPLS VPN Manager, and then click VPN Devices > PE Device List in the
navigation tree. Select one or more PEs. Click Synchronize.
Approach 2
1.
Open global topology or the VPN access topology.
2.
Select a PE.
3.
Select Synchronize.
Verification
•
Click Refresh on the PE device list page to view the synchronization status. After the
synchronization of a device is finished, the system sets the end time as the last synchronization
time of the device.
•
If the VRF configuration of a PE is changed, then on the VPN information page of the PE, the
corresponding SA will prompt the change, otherwise prompt that configuration is unchanged.
•
On the network topology, the VPN links that have configuration changes will be marked with
??.
Switch region
You can move PEs from the region to which they belong to another region with the switch region
function.
Operation procedure
1.
Select one or more PEs in the PE device list or in the region.
2.
Click Switch Region and select the target region.
3.
Click OK.
Verification
•
The region to which the PEs belong is displayed as the selected target region.
•
PEs are in the selected target region in the global and access topology.
Precautions
•
When you modify the region to which PEs belong, switch the region in the same AS.
•
One PE can belong to one region only, and it does not belong to the original region after
region switch.
•
CEs that are connected and in the same region with the PEs belong to the new region after
region switch. CEs that are connected but not in the same region with the PEs still belong to
the original region after region switch.
Remove PE
Remove a PE from MVM. If you remove a PE from the MVM, the PE is still managed by the platform;
if you remove a PE from the platform, the PE is simultaneously removed from the MVM.
76
MPLS Manager