TRI-PHASE OPERATING™ INSTRUCTIONS

94


17.4 Test Plan Loaded Menu


TP# 1

Dyn1

TAPS: 1

TEST PLAN LOADED

1.CONTINUE

.

2.UNLOAD TEST PLAN

Figure 62.0 Test Plan Loaded Menu

a. Description: Confirms that test plan 1 (i.e., “TP#1) is loaded in temporary memory.

Allows the operator to perform a transformer test using test plan 1 or perform a test with the
operator inputting the test parameters (i.e., refer to step 2 of Table 5.0 or step 2 of Table
6
.0). The transformer configuration is set by the test plan and for this example it is a Dyn1.
The number of tests performed is set by the test plan and referred to as “TAPS” and for this
example it is one test.

b. Origin: With a test plan loaded in temporary memory, select menu option 1 from the

“Main Menu”.

c. Action Options: Press key number 1 or push down the Control Knob to use test plan.

Press key number 2 to perform a test without a test plan. Selection of number 2 may be
made by turning the Control Knob and pushing down the Control Knob after number 2 is
selected.

d. Action To Perform: Select menu option 1 for this example.


NOTE:

Selecting menu option 2 results in the display of the “Transformer Configuration Selection First

Menu” (Figure 15.0).