4 test plan loaded menu, Test plan loaded menu, Figure 62.0 – Vanguard Tri-Phase User Manual
Page 94
![background image](/manuals/354155/94/background.png)
TRI-PHASE OPERATING™ INSTRUCTIONS
94
17.4 Test Plan Loaded Menu
TP# 1
Dyn1
TAPS: 1
TEST PLAN LOADED
1.CONTINUE
.
2.UNLOAD TEST PLAN
Figure 62.0 Test Plan Loaded Menu
a. Description: Confirms that test plan 1 (i.e., “TP#1) is loaded in temporary memory.
Allows the operator to perform a transformer test using test plan 1 or perform a test with the
operator inputting the test parameters (i.e., refer to step 2 of Table 5.0 or step 2 of Table
6.0). The transformer configuration is set by the test plan and for this example it is a Dyn1.
The number of tests performed is set by the test plan and referred to as “TAPS” and for this
example it is one test.
b. Origin: With a test plan loaded in temporary memory, select menu option 1 from the
“Main Menu”.
c. Action Options: Press key number 1 or push down the Control Knob to use test plan.
Press key number 2 to perform a test without a test plan. Selection of number 2 may be
made by turning the Control Knob and pushing down the Control Knob after number 2 is
selected.
d. Action To Perform: Select menu option 1 for this example.
NOTE:
Selecting menu option 2 results in the display of the “Transformer Configuration Selection First