4.2

Inspecting the Equipment

1. Carefully check the equipment for possible damage incurred during shipment.

2. Carefully check the equipment against the packing list shipped with the

equipment to ensure that the shipment is complete.

4.2.1 Included

Parts

A typical redundant HPCST-5000 configuration contains the following components.

Notes:

1. Hardware required to perform this task is located in Chapter 8, Equipment List.
2. Because each system can be custom ordered, it is beyond the scope of this

manual to provide the unlimited configuration possibilities.

3. This chapter does not describe the installation procedures for amplifiers, high

performance LNAs, phase-locked LNBs, LNBs, and phase-locked block
converters.