4.5.4 CRS-500 1:N Redundancy System Power-up Sequence

Once all cabling and power connections have been made, power-up of the CRS-500 1:N

Redundancy System should be accomplished in the following order:

Step Procedure

1

CRS-280L IF SWITCH POWER: If the CRS-280L IF Switch is included in the setup, turn both

power switches ON

.

If the CRS-280L is not used, proceed to the next step to turn power on to all modems.

2

MODEM POWER: Turn the power switches ON for all modems.

3

MODEM CONFIGURATION: Configure all modems for 1:N redundant operations as required

per Chapter 5. CONFIGURING MODEMS

FOR

1:N REDUNDANCY.

4

CRS-500 POWER: Turn both power switches (located on the rear panel on the CSU) ON.

As outlined previously and in Chapter 2. INITIAL START-UP

AND

CONFIGURATION CHECK LISTS,

once all components have been successfully powered ON and the modems have been

configured for 1:N redundant operations, the system will be ready for switch operation. Further

information is provided in the following chapters:

Chapter 7. CSU FRONT PANEL OPERATION

Chapter 8. ETHERNET-BASED REMOTE PRODUCT MANAGEMENT (for SNMP, Telnet,

Web Server operation)

Chapter 9. SERIAL-BASED REMOTE PRODUCT MANAGEMENT (for serial remote control

operation)