8 changing the valves and peak information, Changing the valves and peak information -19, Nchanging the valve on/off setting – Yokogawa GC1000 Mark II Process Gas Chromatograph User Manual
Page 48

<3. Analyzer Operation Window>
3-19
IM 11B03G03-03E
3.8
Changing the Valves and Peak Information
The valve on/off timing set in the analyzer can be changed. The individual information (peak
names, gate time, etc.) set for each peak also can be changed. This section explains how to
change these settings.
NOTE
The valve and peak information can be changed only at user level C. This change cannot be
made unless the analyzer is in the Remote mode.
n
Changing the Valve On/Off Setting
(1) Click on the [Valve] command in the [Set Up] menu.
(2) The Valve on/off dialog box pops up.
F0330.ai
Specify the valve number you want to change. The information of the current state is
displayed.
(3) Change the on/off times of the valves, and then click on the [Execute] button. A confirmation
dialog box pops up.
F0331.ai
(4) Click on the [Yes] button.
(5) A message appears to inform you that the data has been changed successfully.
F0332.ai
(6) Click on the [OK] button to finish.
4th Edition : Mar. 21, 2012-00