PROFIT POINT CONSOLE (OPTIONAL)
1.
Verify that the Profit Point and any optional equipment is located in an office type
environment and is correctly installed according to the Site Controller II or Profit Point
Installation Manual.
2.
Verify that the AC power cord for the Profit Point is directly connected to the output of the AC
Surge Protector Strip (C01218).
3.
The RS-485 converter must be installed as described below. If you are locating the Profit
Point more than eight feet from the Site Controller, you must use two additional RS-485
junction boxes to connect the devices.
A modular cable must be directly connected to the modular jack port on the back of the Site
Controller labeled CONSOLE. The other end of the modular cable is connected to one of
the modular jacks on the converter. The converter is connected to the Profit Point port
SERIAL1 via a 25-pin to 9-pin cable. The converter power supply must be plugged into the
same AC Surge Protector Strip (C01218) as the Profit Point.
POS Distribution Box (POS D-Box) is connected via a 9-pin cable from the Serial2 port on
the Profit Point to the Serial2 port on the D-Box. If the site has a PIN Pad, the Serial3 port of
the Profit Point will be connected to the Serial3 port of the D-Box. The D-Box power supply
must be plugged into the same AC Surge Protector Strip (C01218) as the Profit Point.
CASH DRAWER is connected via a 9-pin D-type connector from the cash drawer to the
CASH DRAWER port on the back of the POS D-Box.
CUSTOMER DISPLAY must be installed according to the Site Controller II or Profit Point
Installation Manual. Verify that the Customer Display is connected to the 9-pin CUSTOMER
DISPLAY port on the POS D-Box.
4.
Optional equipment connection:
RECEIPT PRINTER connection depends upon the type of receipt printer ordered. For a
parallel printer, the printer cable is connected to the D-type 25-pin female connector
PRINTER on the back of the Profit Point. For an RS-485 printer, the modular cable is
connected directly into the RS-485 jack on the converter. The receipt printer must be
plugged into the same AC Surge Protector Strip as the Profit Point.
PIN PAD must be installed according to the Site Controller II or Profit Point Installation
Manual. Verify that the PIN pad is securely connected to the PIN PAD port located on the
POS D-Box.
SCANNER must be installed according to the Site Controller II or Profit Point Installation
Manual. Verify that the Scanner is securely connected to the 9-pin SCANNER port located
on the POS D-Box. If a scanner is used that needs external power, it must be plugged into
the same AC Surge Protector Strip as the Profit Point.