Commissioning the safety system, 1 preparing for commissioning, 3safety mat/safe edge – Pilz PNOZ m1p base unit User Manual

Page 32: 5 commissioning the safety system

background image

Pilz GmbH & Co. KG, Felix-Wankel-Straße 2, 73760 Ostfildern, Germany
Telephone: +49 711 3409-0, Telefax: +49 711 3409-133, E-Mail: [email protected]

3-5

3.5

Commissioning the safety system

3

Safety Mat/Safe Edge

3.5

Commissioning the safety system

3500

Commissioning the safety system

3-

Schaltmatte_Sicherheitssystem in Betrieb nehmen-einleitung

When using the pressure-sensitive protective device, please note the

following:

The following are not permitted: Walking aids such as canes and

wheeled vehicles

3.5.1

Preparing for commissioning

Preparing for commissioning

3-

Schaltmatte_Sicherheitssystem in Betrieb nehmen-vorbereiten

Please note the following when preparing for commissioning:

Cables that have to be laid outside the control cabinet must be pro-

tected from mechanical damage, e.g. by installing them in a conduit.

Pressure-sensitive protective devices may not be fitted with a termi-

nating resistor.

The configured test pulse outputs should be used exclusively for test

pulses on the pressure-sensitive protective devices. Be sure to note

the information provided in "Technical details".