Do Items Below in the Order Listed
For Details Go To
5. Momentarily press the LMPTST switch on the APU front panel
and verify that all indicators light.
6. Connect terminal equipment to Craft port on the front of the MPU.
7. Log on to the Craft Interface.
9. Enter Target Identifier and set date and time now or during
provisioning (the turn-up process).
10. Configure DS3 MUX as required.
11. Configure ODS2 modules as required.
12. Clean and mate fiber optic connectors and adapters as required.
13. Connect the test equipment at both ends of the system and perform
an end-to-end test between the Soneplex chassis and the remote
module.
14. If the Soneplex system being tested is equipped with protection
modules:
Execute Force/APS commands through the Craft Interface.
Perform Manual (Force) Switch to Protect test on DS3 MUX
module.
Perform APS test on DS3 MUX module.
Perform Manual (Force) Switch to Protect Test on ODS2 module.
Perform APS test on ODS2 module.
15. Log off from the Craft Interface system.
16. Complete assignment forms and update office records as required by