FEC Micro Nutrunner Operations Manual

Chapter 8: Maintenance and Inspection (Rev. 2: 02/12)

Page 8-3

8.1.3 MNR Unit

Recommended Schedule: Quarterly

The MNR Unit requires careful use and handling. Inspect each MNR Unit and ensure the
following requirements are met:

1. The environmental conditions are within specifications.

2. There is no moisture, oil, or foreign matter on the unit.

3. The unit is securely mounted, with appropriate clearance on all sides.

4. All screws (for the cover of the unit and for mounting) are correctly tightened.

5. The input power remains within specifications at all times.

6. The unit is not producing any abnormal (excessive) heat.

7. Unit cables (on the front and the underside) are securely fastened and without damage.

8.1.4 Air Handling Units (Air Conditioner, Heat Exchanger, etc.)

Recommended Schedule: Every 2 months (sooner if external environment is harsh; IE: machining
area with coolant mist in air).

Equipment supporting the Micro NR system environment must be sufficiently maintained. Internal
electrical enclosure (which the MNR Units are housed) heat load can be calculated using the
internal power consumption data in table 2.3. Verify support equipment meets the following
requirements, as applicable to the unit type:

1. The unit is free from dust, oil and foreign matter.

2. All filtration devices are clean and air flow is not impeded.

3. The unit is securely and correctly mounted.

4. The input power remains within specifications at all times.

5. All fans are functioning properly with no abnormal sound or vibration.