4 installation, Preparation – GE Industrial Solutions CPS6000-M2 User Manual
Page 28

CPS6000-M2 Installation Guide H5694720
Issue 8 January 2008
28
4 Installation
This section describes the following installation sequence for the CPS6000-M2 power system.
1. Preparations
2. Anchoring
frame
3.
Connecting frame ground
4.
Connecting CO ground
5.
Connecting ac utility
6. Installing
batteries
7.
Wiring dc loads and installing fuses/circuit breakers
8.
Installing rectifiers and converters
9.
Controller Connections
10.
Starting Up System
Preparation
Safety
Please review all safety warnings in Section 3 before beginning the installation process. Observe
all warnings and labels on the equipment.
WARNING: Due to the possibility of working on energized circuits during these
procedures, all tools and test equipment must be insulated in an approved manner.
Proper ESD protection is required in order to prevent ESD damage to the
equipment.
WARNING: Only qualified personnel should install and service the power
system and plug-in modules. Hazardous energy and voltages are present in the
unit and on the interface cables and will shock or cause serious injury or death if
safety precautions are ignored. Follow all safety warnings and practices when
servicing this equipment.