INSTALLATION AND GROUNDING
SECTION
4.1.
GENERAL
This section provides the installation procedures for the CommVerter, and the removal instructions
for sub-module replacement. Paragraphs 4.2 to 4.4 provide the installation procedures specifically
for the enclosed type Commverter unit only.
4.2.
PRELIMINARY PROCEDURES
4.2.1.
Unpacking and Inspection
This section provides information for unpacking and inspection:
Examine the shipping container for damage before unpacking the
unit. Perform a visual inspection to reveal any physical damage to
the equipment.
Verify that the equipment is complete, as listed in Table 4-1.
4.2.2.
Installation Equipment
The CommVerter is supplied in a kit with the necessary items for its proper installation, as listed
below.
Table 4-1
.
CommVerter Unit
Kit
No.
Description
1
CommVerter Unit
2
Connector for RS-485 / RS-232 / Current Loop / Tokheim and more
3
Mounting Bracket for wall installation
NOTE
The kit includes the relevant connector only (Item 2), in
accordance with the supported communication conversion
method.
8 Port CommVerter Operation and Installation Manual