• Adjust the side plate (5) of the trolley inwards by turning the screws (3) until there is a gap of
approximately 3…5mm between the flange of the travel wheels and the flange of the beam.
• Adjust the position of the trolley so that the hook is hanging below the centerline of the beam. Lock
the position by tighten the nuts (2).
!
Tighten the nuts (2) and the screws (4) to the correct tightening torque. Refer to the section
'Recommended tightening torques'.
6.5.3 Outfitting the hoist
• Install the power supply. Refer to the section “Connecting the to mains network”.
• Adjust the limit switch for hoisting. Refer to the section “Adjusting hoisting limit switch”.
• Carry out the commissioning inspection and complete the commissioning log. Refer to the section