6.4 Double-girder

trolley

c_dab1a

1. Travel wheel
2. Rail


• Remove the temporary transport supports. Take the hoist out of the packing and move it to the

installation site. Lift the hoist using the lifting lugs provided.

• Check that the rail centers (B) on the main beam are suitable for the hoist trolley.

• Check that the groove (C) in the travel wheel is 15 mm wider than the rail width (A).

• Lift the hoist trolley onto the track.

• Check the proper installation and position of the runway end stops.
• Check that the hoist buffers are able to bump into the runway end stops or buffers of other trolley.

Note that in some hoist models the position of buffers can be changed.


6.4.1 Outfitting the hoist

• Install the power supply. Refer to the section “Connecting the to mains network”.

• Adjust the limit switch for hoisting. Refer to the section “Adjusting hoisting limit switch”.
• Carry out the commissioning inspection and complete the commissioning log. Refer to the section

“Commissioning”.