beautypg.com

2 dry load column, preparation, 3 prep hplc column, installation – BUCHI PrepChrom C-700 User Manual

Page 48

background image

5 | Installation

BÜCHI Labortechnik AG

48/110

PrepChrom C­700

u

Tighten the knurled knob (1) to secure the upper holder.

5.5.2 Dry load column, preparation

u

Set up a dry load column according to:

5.5.1 Flash/prep column, preparation [

}

page 47]

5.5.3 Prep HPLC column, installation

Preliminary tasks

u

Install the tube between the upper column holder and port no 3 of the 6­
way electrical valve.

u

Install the tube between the lower column holder and the inlet of the
UV Detector module.

Tasks

u

Tighten the lower knurled knob (2).

u

Position the column (4) on the lower holder and tighten the PEEK
adapter (3).

NOTE

Hold the HPLC column during installation due to its weight.