Preface
If the drawings require changes to suit the installation and application of the
system, fax or e-mail the marked up drawings to the Start-up Project Manager.
Shipping, Handling, and Installation Manual
Review publication
Variable Frequency Drive Shipping, Handling, and Installation manual.
The customer/contractor has the option to perform the electrical
interconnection work between cabinet shipping splits, as shown in this manual,
or contract Rockwell Automation to perform this work. This will be reflected in
the Services Purchase Order and the pre-commissioning checklist. Verify that the
documentation matches the actual scope of work done by the customer/
contractor. You will be required to either perform this interconnection work
immediately prior to the commissioning process or to verify the work was done
correctly by the contractor. It is very important to confirm the alignment of the
paperwork with the actual scope of work.
It is also extremely important to understand the contractor’s basic scope of work,
preceding the commissioning process. Part of the overall commissioning process
is to ensure this work has been done correctly. If this work has not been done
properly, this must be brought to the attention of the customer immediately. Do
not proceed with commissioning until this issue is resolved.
Additional required information about the PowerFlex 6000 can be downloaded
from
•
: PowerFlex 6000 Medium Voltage Variable
Frequency Drive Shipping, Handling, and Installation Instructions
•
: PowerFlex 6000 Medium Voltage Variable
Frequency Drive User Manual (operating the HMI, full parameter listing)
You must review these publications thoroughly before beginning the
commissioning process. They contain supplemental information that will aid in
the commissioning process.