beautypg.com

Electrical installation inspection, Power cabling, Electrical installation inspection power cabling – Rockwell Automation 6000 PowerFlex Medium Voltage Variable Frequency Drive Commissioning Manual User Manual

Page 22

background image

22

Rockwell Automation Publication 6000-IN007A-EN-P - October 2014

Chapter 2

Preparation and Inspection

Electrical Installation Inspection

Power Cabling

Trace the power cabling from termination point to termination point while
examining the cable and its routing for mechanical damage, sharp bend radiuses
and sources of induced noise and heat. The power cabling must be is sufficiently
braced to contain the cabling in the event of a ground fault. Color coding is used
to indicate the phase orientation of the drive.

Sequence

Task

Reference
Document

1

Verify that medium voltage cables are separated at least 30 cm from the control cables

2

Verify that all secondary control wiring use shielded cables

3

Verify that input and output medium voltage cables specifications meet the stated
insulation requirements

Electrical
Drawings

4

Verify that input and output medium voltage cables have attached nameplates

5

Verify the diameter of control power cables comply with the drawings

Electrical
Drawings

6

Verify that the electrical safety circuit wiring between the input circuit breaker and the drive
is shielded and only the end at the drive side is grounded

7

Verify the wiring between the DCS and the drive is shielded and only the end the drive side is
grounded

8

Verify that the user-provided ground cable is ≥50 mm

2

9

Verify the isolation transformer’s primary input voltage matches the system primary voltage

10

Verify that the customer motor specifications match the drive voltage and current
capabilities

11

Verify that the isolation transformer’s input side wiring is correct

Electrical
Drawings

12

Verify that the motor output side wiring is correct

Electrical
Drawings

13

Verify all external control wiring is terminated correctly and to the proper terminal blocks

Electrical
Drawings

14

Verify torque on incoming line power cable and outgoing motor power cable terminations

Electrical
Drawings

Table 6 - Color Coding

Color

Incoming Line Side

Outgoing Motor Side

Yellow

L11 (A Phase) Line Cable Terminal

U Phase:
Power Module Bus
VSB Input Cable
Motor Cable Termination
Motor Cable Connection to Power Module Bus

Green

L12 (B Phase) Line Cable Terminal

V Phase:
Power Module Bus
VSB Input Cable
Motor Cable Termination
Motor Cable Connection to Power Module Bus

Red

L13 (C Phase) Line Cable Terminal

W Phase:
Power Module Bus
VSB Input Cable
Motor Cable Termination
Motor Cable Connection to Power Module Bus