beautypg.com

Interconnection review – Rockwell Automation 6000 PowerFlex Medium Voltage Variable Frequency Drive Commissioning Manual User Manual

Page 20

background image

20

Rockwell Automation Publication 6000-IN007A-EN-P - October 2014

Chapter 2

Preparation and Inspection

Interconnection Review

The interconnection checklist summarizes the required items to review to
validate the reconnection of power, ground, and control cables between cabinets
within the drive system, that were disconnected for shipment. Power and control
cables that pass from one cabinet to another are bundled in the appropriate
cabinet. These cables are connected for system test at the factory but
disconnected and coiled up for shipment. If this interconnection work was done
by the contractor, use this checklist to review and ensure the work was done
correctly. If the interconnection work was not done by the contractor, the scope
of work required to be performed is described in

6000-IN006_-EN-P

.

.

IMPORTANT

Check torque on all power and ground cable connections per specifications
listed in

Torque Requirements on page 81

.

Table 5 - Interconnection Review Checklist

Bypass Cabinet (if supplied)

Isolation Transformer Cabinet

Power Module Cabinet

Low Voltage Control Cabinet

Front Inspection

Verify the braided ground
connection to adjacent cabinet(s)
is properly installed
Review the braided ground
connection to adjacent cabinet
Verify line and load power
cables from Isolation Transformer
Cabinet are properly connected
Verify all control wires per
Electrical Drawing

Verify the braided ground
connection to adjacent cabinet(s)
is properly installed
Review all isolation
transformer secondary wiring
from Power Module cabinet
(2 sets)
Verify that the shields of all
of the system’s connecting wires
are properly grounded
Verify all control wires per
Electrical Drawing

Cables are run in LV cable

sections along front and
back of cabinet

Verify the braided ground
connection to adjacent cabinet(s)
is properly installed
Verify that the shields of all
of the system’s connecting wires
are properly grounded
Review load power cable
connection from Isolation
Transformer Cabinet
Verify Voltage Sensing
Board power cables from Isolation
Transformer Cabinet are properly
installed

Verify control signal wiring
bundles from LV Control cabinet
to LV panel in Isolation
Transformer cabinet and LV panel
in the Bypass Cabinet (if supplied)
are routed correctly

Rear Inspection

Fixed Mounted Power
Module:
Verify all isolation
transformer secondary windings
from Power Module Cabinet are
properly connected (1 set)
Drawout Power Module:
Verify all isolation
transformer secondary windings
from Power Module Cabinet are
properly connected (3 sets)
Verify all power supply
cables for main cooling fans for
Isolation Transformer Cabinet are
properly connected(3 sets)