Service, 4 how to replace device components, 1 service warranty – KROHNE OPTIWAVE 5200 C_F EN User Manual
Page 91
SERVICE
7
91
OPTIWAVE 5200 C/F
www.krohne.com
07/2013 - 4001904902 - HB OPTIWAVE 5200 R02 en
How to use the purge
7.3 Heating or cooling horn antennas under process conditions
A heating / cooling system option is available for DN150 / 6¨ and DN200 / 8¨ Metallic Horn
antennas. The outer surface of the antenna is sealed in a metal heating / cooling jacket.There is
an inlet and an outlet for the heating / cooling jacket on the top of the flange. For more data
about dimensions, refer to
Dimensions and weights
on page 116 (Purging and heating/cooling
system options).
It is also possible to use a purging system with the heating / cooling system. For more data,
refer to
How to clean horn antennas under process conditions
on page 90.
7.4 How to replace device components
7.4.1 Service warranty
Servicing by the customer is limited by warranty to:
• The removal and installation of the device.
• Compact version:
Compact version:
Compact version:
Compact version: The removal and installation of the signal converter (with the weather
protection, if this option is attached). For more data, refer to
How to turn or remove the signal
converter
on page 37.
WARNING!
Purge the antenna with a dry gas or liquid that is applicable to the process. For more data, refer
to the table that follows:
Process conditions
How to use the purge
The device is colder than other
elements in the process. It is
possible that there will be
condensation in the antenna.
Continuous use. Use low-pressure gas to remove condensation from
the antenna.
There is a risk of build-up in the
antenna
Purge at intervals. Use compressed air, nitrogen or another gas that
is applicable to the process up to 6 bar / 87 psi.
There is a build-up or risk of
build-up in the antenna
Purge at intervals. Use a liquid (hot water, solvent or another liquid
that is applicable to the process) to melt the liquid that has
crystallized on the antenna.
WARNING!
Make sure the the pressure in the heating / cooling system is not more than 6 bar / 87 psi.
Make sure that the flange temperature is not more than the maximum limit. For more data, refer
to Technical data on page 101
.
WARNING!
Only approved personnel can do an inspection of the device and repairs. If you find a problem,
send the device back to the supplier for inspection and/or repairs.
INFORMATION!
The converter housing (compact or remote version) can be detached from the process
connection assembly under process conditions. For more data, refer to How to turn or remove
the signal converter on page 37
.