5. Operation and Maintenance

9128-A2-GB20-60

April 2002

5-71

ISDN DBM Operation

The following sections only apply to units with an ISDN DBM:

T

Forcing Backup (Disruptive)

T

Placing a Test Call (Nondisruptive)

T

Verifying ISDN Lines

T

Verifying That Backup Can Take Place

Forcing Backup (Disruptive)

Use this procedure to force backup when network maintenance is planned, when
equipment problems are reported, or when testing the backup path – whenever
data needs to be forced from the primary destination interface to the alternate
destination, typically from the T1 network to the ISDN.

Procedure

1. Make sure the ISDN Link Profiles are set up correctly, Auto Backup is enabled,

and the ISDN interface is enabled (see

Setting Up Dial Backup

in Chapter 3,

Configuration).

2. Have someone at the far end disconnect the network cable to initiate backup.

3. Verify that backup is taking place.

See

Verifying That Backup Can Take Place

on page 5-73

.

NOTE:

When an alarm requiring backup is received, backup can be manually
controlled by enabling or disabling the Auto Backup option (see

Step 2

).

4. Have the far-end network cable reconnected to return to standard operation.