beautypg.com

Frame installation – Alamo TS-100A User Manual

Page 49

background image

© 2005 Alamo Group Inc.

Section 5 - 9

Maverick (NH TS-100A,115A ,125A/,35A Asy. Man) 01/05

Frame Installation

3.

Install Rear Frame Mount Rails. Rear frame

rails consist of a LH & RH. We have started with the
Left Hand Rail. The three point lift stabilizer brackets
will need to be unbolted on both sides. In the illustra-
tion for the LH side we installed the frame with the
LH rear tire and wheel still removed, this was done
for clarity not because the wheel needs to be re-
moved. Using a floor jack to lift the rail up under the
rear axle (Stabilizer brackets for three point have
been unbolted). Install the bolts up and into the three
point stabilizer bracket and the tractors rear axle
housing and snug the bolts down. Support the frame
rail with a jack stand (or leave the floor jack under it).
(See Figure 17 & 22).

The RH Rear Frame Rail will basically install

the same, bolts up under the tractor axle housing
with the three point stabilizer bolt back up under
frame rail (See Figure 18 & 23). The RH Rail looks
different at the rear because the boom rest will bolt
here later.

4.

Install Front Frame Mount Rails. The Front

Frame mount rails will consist of a RH & LH (See
Figure 19, 20, 24 & 25) These will only fit one way as
they have a gusset reinforcement on one side that
will be showing to the outside when installed. These
can be lifted by the technician installing them. The
LH and RH will install the same way, Using 4 bolts
each that screw into tractor casting on the side of
the tractor (See Figure 24). Make certain that all 3/4"
and 20 mm bolts have hardened flatwashers on
them.

Figure 22

LH Rear Frame

Mount Weldment

P/N 02982006

Figure 23

RH Rear Frame

Mount Weldment

P/N 02982005

3 Point Stabi-

lizer Bracket

Figure 24

RH Front Frame
Mount Weldment

P/N 02982015

Figure 25

LH Front Frame

Mount Weldment

P/N 02982014

This manual is related to the following products: