beautypg.com

Setup: 04i gen warm-up time menu, Setup: 04j gen cooldown time, 2 me-ags-n functional tests using the me-rtr – Magnum Energy AGS Network (ME-AGS-N) User Manual

Page 79: 0 using the me-rtr router

background image

73

© 2012 Magnum Energy, Inc.

10.0 Using the ME-RTR Router

Set Gen Warm-up Time This setting is the amount of time the gen-

erator is allowed to warm up before connecting to the inverter/charger.
Default setting: Set Gen Warm-up Time = 60 sec.
Range: OFF, 1 - 120 Seconds, 3 - 127 Minutes

Where should I set Gen Warm-up Time? Check with your generator manu-

facturer. Typically, smaller generators (~2-3 KW) need at least 60 seconds

before applying a load; larger generators require a longer warm-up time.

SETUP: 04J Gen Cooldown Time
This menu allows the generator to continue to run after it disconnects from

the inverter/charger and prior to autostopping (i.e., cool down). Allowing

the generator to cool down after the load is disconnected helps to prolong

generator engine life (especially diesel engines w/turbos).

Set Gen Cooldown Time This setting is the amount of time the genera-

tor is allowed to cool down after it disconnects from the inverter/charger.
Default setting: Set Gen Cooldown Time = 60 sec.
Range: OFF, 0 - 120 Seconds, 3 - 127 Minutes

Where should I set Gen Cooldown Time? Check with your generator

manufacturer. Typically, smaller generators (~2-3 KW) need at least 60 sec-

onds to cool down after being disconnected from a load; larger generators

require a longer cooldown time.

Info: The warm-up and cooldown features prevent the generator

from connecting to the inverter’s AC input. Since the inverter only

has a single-source input, it can not distinguish between grid or

generator input. So, during warm-up or cooldown, the inverter will

prevent any AC input from connecting. When either warm-up or

cooldown is activated, it will disconnect any AC source connected to

the inverter’s AC input (i.e., grid or generator) until the time period

(warm-up or cooldown) is over.

SETUP: 04I Gen Warm-up Time Menu
This menu allows the generator to run (i.e., warm up) before it connects to

the inverter/charger, or powers the battery charger and any pass-thru loads.

Most generators need to warm up before a load is supplied – similar to warm-

ing up your car before driving it.

10.2 ME-AGS-N Functional Tests using the ME-RTR

Once you have used your ME-RTR router to establish all the autostart/autostop

settings you need, perform the following tests to verify that the AGS system

is functioning correctly and the communication from the remote/inverter to

the ME-AGS-N is correct.

10.2.1 Router to Generator Communication Test

This section describes how to: access the AGS Home screen, determine the

current AGS status, and use the ME-RTR router to start the generator.

10.2.1.1 Accessing the AGS Home Screen

In order to access the AGS’s CTRL, METER, and PORT menus, you must

fi rst ensure that you are on the port that displays the AGS Home screen.

Once the AGS Home screen displays, press the particular router button to

access the desired AGS menu.