1 contact protection, 1 leakage current, 6wiring – Pilz PMCprotego D.72/000/0/0/2/208-480VAC User Manual
Page 114

6.3
Notes on wiring
6
Wiring
Pilz GmbH & Co. KG, Felix-Wankel-Straße 2, 73760 Ostfildern, Germany
Telephone: +49 711 3409-0, Telefax: +49 711 3409-133, E-Mail: [email protected]
6-6
Please note the following safety guidelines:
][Verdr_nie_unter_Spg_1_D_48_72
][Verdr_nie_unter_Spg_2
6.3.1
Contact protection
Contact protection
6-
6.3.1.1
Leakage current
Leakage current
6-
][Verdr_Ableitstrom
The leakage current via the protective earth conductor is the sum of the
leakage currents from the units and cables.
The frequency of the leakage current is made up of a number of frequen-
cies. The residual current devices evaluate the 50 Hz current. It's not
possible to measure the leakage currents using a conventional multim-
eter because these too are standardised at 50 Hz current.
DANGER!
Risk of electrocution!
Never unplug the electrical connections on the servo amplifier
while voltage is applied.
Switch off the supply voltages!
Residual charges in the capacitors may still show hazardous val-
ues for up to 10 min. after the mains voltage is switched off.
Measure the voltage on the intermediate circuit (+DC/-DC). Wait
until the voltage has dropped below 40 VDC.
Wait at least 10 minutes before touching any parts that carry
voltage (e.g. contacts) or loosening the connections.
DANGER!
Risk of electrocution!
Never wire the electrical connections on the servo amplifier
while voltage is applied.
Switch off the mains voltages and 24 V supply!
Make sure that the control cabinet is made safe, e.g. through an
access lock or warning signs. Do not switch on the voltages until
the system is commissioned!