Pre-Commissioning Responsibilities

Ensure that the customer has completed the pre-commissioning checklist; refer to
the PowerFlex 7000 ‘B’ Frame Installation Guide for the customer’s full pre-
commissioning checklist, as well as sign-off dates and signatures indicating
completion of the required tasks.

Commissioning Preparation

The following section identifies all the tools and resources required to
successfully commission a PowerFlex 7000 ‘B’ Frame drive line-up. In addition, it
identifies how to obtain the required equipment in the event that it is not readily
available prior to commissioning the drive. It is recommended that all items listed
below be obtained prior to attempting to commission the drive. Ensure that the
contents of this section are reviewed and that the uses of the equipment described
within are understood prior to commencing commissioning of the drive. If
further support or additional information is required, contact your local
Rockwell Automation service office or Medium Voltage Support at (519) 740-
4790.

Recommended Tools and Equipment

Hand Tools

• Metric and Imperial wrenches, sockets, and Hex keys
• Torque wrench
• Assortment of screw drivers
• Assortment of electrical tools (wire strippers, electrical tape, crimpers, etc.)

Electrical Equipment

• High voltage gloves – 10 kV insulation rating (minimum)
• Approved high voltage potential tester – 10 kV rating (minimum)
• Anti-static strap

Test Equipment

• 100 MHz oscilloscope with at least 2 channels and memory
• 600-Volt (1000V rating) digital multimeter with assorted clip leads
• 5000 Volt megohmmeter

Computer Requirements and Software

• Laptop computer (486 or higher installed with Microsoft (MS) Windows)
• Microsoft HyperTerminal (Provided with MS Windows)
• Rockwell Automation Software (RS) drive tools (Optional)
• RS Logix 2
• Required computer cables