5.
Press the F3=Exit key.
The screen display changes to the Edit Logical Path Definition panel.
6.
When defining a path from the secondary site to the primary site, specify e in the AC column
on the Reverse line.
If no path is to be defined from the secondary site to the primary site, steps 6 through 10 do
not need to be performed.
Edit Logical Path Definition
Command ===>
2008/02/28 16:03:38
Path Set ID . . . : TESTPATH
Description . . . : TEST
Attributes
Type . . . . . . . . CU (DKC/CU)
SHR . . . . . . . . Y (Y/N)
Supported action: s(Select Storage System)
AC S/N Model IFType PathID CU SSID CCA
Primary 14002
USP
1515
00
2340
1F
Secondary 14001
USP
1515
00
2350
1F
Supported action: e(Edit physical path)
AC Assigned Physical Path
Forward 04->05
e Reverse
F1=Help F3=Exit F7=Backward F8=Forward F12=Cancel
7.
Press the Enter key.
The Edit Port Definition panel appears.
Edit Port Definition
Command ===>
Scroll ===> PAGE
2008/02/28 16:06:29
Supported action: d(Delete)
Path Set ID . . . : TESTPATH
Description . . . : TEST
S/N Model IFType PathID CU SSID
Primary . : 14002 USP 1515 00 2340
Secondary : 14001 USP 1515 00 2350
-------- Port ---------
AC Primary Dir Secondary
******************************* Bottom of data ********************************
F1=Help F3=Exit F5=Add F7=Backward F8=Forward F12=Cancel
8.
Press the F5=Add key.
The Assign Port panel displays.
9.
Specify 05 for Primary Port Number and 04 for Secondary Port Number.
Edit Port Definition
Command ===> ADD Scroll ===> PAGE
.----------------------------------------------. 8/02/28 16:06:29
Supported a | Assign Port |
Path Set ID | Command ===>
|
Description | |
Creating a path set 539