Power+ routine start-up, 1 start-up after shutdown, Power – MaxPower Corp Gamatronic Power+ RM100 User Manual
Page 73: Routine start, Start-up after shutdown, Igure, Ain screen after a power shutdown, Ain screen after a power shutdown indication, Ain screen at power
Gamatronic Electronic Industries Ltd.
POWER+ RM100,
3
X
208
V, User Guide, Release 2.7ys
57
6.
POWER+
ROUTINE START
-
UP
6.1
Start-up after Shutdown
This section describes the start-up procedures for the operator after a POWER+ shutdown.
After shutdown, the UPS on, Alarm and Load indicators will flash.
After a normal POWER+ shutdown the display screen indicates a load of zero amps, the UPS
status is “OK, OFF”; the Static Switch status is “OK, BYP”.
LOAD LEVEL ---22:21:18---
L1:__________ 000A, 120V BATTERY: 432V
L2:__________ 000A, 120V UPS OK (OFF)
L3:__________ 000A, 120V STSW OK (BYP)
Figure 65: Main screen after a power shutdown
Figure 66: Main screen after a power shutdown indication
1.
Press twice on the On/Off button on the upper right of the system controller panel.
Wait about 2 minutes for the POWER+ to start up.
The following screen is displayed:
LOAD LEVEL ---22:21:18---
L1:__________ 000A, 120V BATTERY: 432V
L2:__________ 000A, 120V UPS OK (ON)
L3:__________ 000A, 120V STSW OK (INV)
Status
indications
Figure 67: Main screen at power-up
Observe that UPS OK indication is now ON and the STSW OK now indicates INV.