Checks to be performed following initial startup, Able, Hecks after initial startup – MaxPower Corp Gamatronic Power+ RM100 User Manual

Page 61

background image

Gamatronic Electronic Industries Ltd.

POWER+ RM100,

3

X

208

V, User Guide, Release 2.7ys

45

5.11

Checks to be performed following initial startup

Table 10: Checks after initial startup

TYPE OF CHECK

REQUIREMENT

RESULT

3-3 configuration

L1-L2
L2-L3
L3-L1

Phase-to-phase:
Not less than 2 %
below no-load values
measured in item 5
below.

2-2 configuration

L1-L2

3-3 configuration

L1
L2
L3

1.

Ac input voltage during operation under load.
Take measurements on the input terminals of
the system

Phase to Neutral:
Not less than 2 %
below no-load values
measured in item 5
below.

2-2 configuration

L1
L2

2.

With no load on the system, measure current
circulation between the units.

I

rst should be <10 A

3.

With no load on the system, measure the dc
voltage of the system.

Total dc voltage between + and –
terminals should be between 384 V and
432 V.

(+) — (–)

4.

Voltage between neutral and ground during
operation under load
On the input terminals of the system

0–2 Vac

5. System output voltage

120 V +/- 2 %
or other according to system specifications

6. Total system load / output current

Verify that the system is not overloaded in
relation to system specifications

7. Correct and orderly operation

Verify that the UPS is operating normally in
accordance with this User Guide and that no
alarms or fault indications are evident

NOTE: It is the responsibility of the customer to notify Gamatronic Electronic Industries Ltd. and receive

approval for any deviations from these requirements.

T

O COMPLETE THE INSTALLATION CHECKLIST

,