Final works, Installation check – Lenze EVF9333 User Manual
Page 212

Final works
Installation check
6
l
212
EDKVF9333V DE/EN/FR 7.1
6
Final works
6.1
Installation check
(
Stop!
Destruction of the digital outputs (X5/A1
X5/A4).
The digital outputs are not protected against external voltage.
Possible consequences:
ƒ
Applying an external voltage to X5/A1
X5/A4 can damage the digital
outputs. The control card does not work correctly any longer.
Protective measures:
ƒ
Never apply an external voltage to the terminals X5/A1 X5/A4.
After completing the installation, the following must be checked:
ƒ
Wiring for completeness, short−circuit, and earth fault
ƒ
In−phase connection of the mains cable
ƒ
In−phase connection of the motor cable (direction of rotation)
ƒ
If necessary, direction of rotation of the incremental encoder
)
Note!
The installation check is followed by commissioning. Further information can
be obtained from the System Manual for the drive controller.
ƒ
Read the System Manual carefully before you switch on the controller!
ƒ
Carry out the commissioning steps in accordance with the System Manual!
ƒ
If you use the "safe standstill" function, check the function of the circuit!