3
TS-LLD System Operation & Testing
System Operation
The TS-LLD system can perform three different
pressurized line leak tests, two
of which run automatically. The automatic line leak tests are: a
gross
3.0 gph
hourly test, and a
standard
0.2 gph monthly-compliance test. The third test is a
precision
0.1 gph annual test that must be started manually at the control unit...
the 0.1 annual test is also known as a
manual test
.
A
Quick Reference Guide
is provided with every TS-LLD system. It was designed
specifically for use by your customer at his station. Inform your customer to keep
a log of all alarm and error codes. This log could be FAXed to you and would
prove to be very useful diagnostic tool.
Distributors and Installers: you may
order more guides by contacting
INCON and asking for part number 000-1447 or
for 000-1482, which is a color-laminated version. Certain restrictions may apply.
Need Help ?
Call INCON Technical Service
@
1-800-984-6266 (or FAX: 1-207-282-9002) for
help with leak alarms, or diagnostic codes. Also, please call if alarms, warnings,
or error codes occur frequently or repeatedly.
DANGER
This line leak detector may start the pump at any time during a line
leak test to maintain fuel line pressurize.
Avoid Fire, Explosion hazards, and
Electrical shock hazards... make sure that all dispenser and submersible
pump power is turned off / locked out before attempting any service (such as:
replacing fuel line filters).
Inspect the copper Mineral Insulated Cable (MI Cable)
at the Leak Sensing Unit for damage, kinks, or breakage. Make sure to do this
after any installation or service is done in the containment sump / pump head and
BEFORE power is applied. See Chapter.Section 2.2 in this manual about
installation and inspection.
Never apply power if the MI Cable is damaged !
Contents:
•
System Operation
•
Normal Displays (Day Counts, Diagnostic Codes)
•
Fault displays (Test fails, Monthly Compliance Warnings)
•
Indicator lights, RESET-TEST button USE
•
Starting a 0.1 Manual Precision Leak Test
•
Normal Operation (Sequence of Events)
•
Out of Compliance (Dispensing Disabled)
•
Frequently Asked Questions
•
What to do: When a Leak Test Fails ? (Leak is Detected)