LSU

Installation

Page

2.2
-

15

2.2

Figure 2.2-15 INCON TS-LLD Installation at BigFlo Diaphragm Valve

To / From

Pump Control

Relay Box &

3 Phase

Motor

Starter

Underground

Containment / Storage Tank

To Dispenser

From #

3 Phase

Motor

Starter

To

Pump

Control

Relay

Box

3/4 inch Conduit

& EYS Epoxy filled

" Y " Seal fittings

A

A

or

BigFlo

STP

Pump

BigFlo

STP

Pump

Crouse-Hinds:

GUAD

or GUAM

& GUJC

Crouse-Hinds:

GUJC Explosion-

proof Junction Box

A 3/4 TO 1/2 inch

bushing is also

required for the

TS-LLD LSU fitting

3/4 inch

Conduit

& EYS

Epoxy filled

" Y " Seal

fitting

INCON

TS-LLD

Line Leak

Detector LSU

Diaphram

Valve

A

A

UL approved

Explosion Proof

Junction Boxes

Class 1, Div's 1 & 2

Groups C, D

MI Cable

Detail A

BIG-FLO PUMP & DIAPHRAGM VALVE

Installation (2 Explosion proof Conduit Outlet

Boxes & Hardware and 1 conduit run)

Detail B Alternate

BIG-FLO PUMP & DIAPHRAGM VALVE

Installation (2 Explosion proof Conduit Outlet

Boxes & Hardware and 2 conduit runs)

Note: Use two conduits when conduit fill exceeds 40% full as specified by your National Electric Code.

Reference Schematic

Figures 2.3 - 9 & 10

Use recommended components or equivalent