Mechanical loading
— Mount the equipment in the rack so that uneven
mechanical loading does not create a hazardous condition.
•
Circuit overloading
— When connecting the equipment to the supply
circuit, consider the connection of the equipment to the supply circuit and
the effect that circuit overloading might have on overcurrent protection and
supply wiring. Consider equipment nameplate ratings when addressing this
concern.
•
Reliable earthing (grounding)
— Maintain reliable grounding of rack-
mounted equipment. Pay particular attention to supply connections other
than direct connections to the branch circuit (such as the use of power strips).
Rack mounting procedure
For optional rack mounting, do not install the rubber feet. Mount the MGP in the
rack as follows:
1
.
Attach the included rack/through-desk mounting brackets (part #70-155-01)
to the unit, using eight of the machine screws supplied with the mounting kit.
(See the illustration below.)
2
.
Insert the unit into the rack and align the holes in the mounting brackets with
the holes in the rack. Use four machine screws to attach the brackets to the
rack.
MBD 249
2U Rack Mounting
Bracket (Use four
lower holes.)
Rack mounting an MGP 464/462xi