Initial power up of the system, Rectifier installation notes – GE Industrial Solutions Galaxy Power Systems User Manual
Page 188

Installation Guide for Galaxy Power Systems
15 - 4 Power Up and Installation Completion
Issue 12 August 2012
Initial Power Up of the System
Initial Power Up of the System
Step
Action
1
To turn up the system while using the factory default firmware and
software loaded in the controller, proceed as follows:
Warning
Before proceeding with the initial power up of the system,
verify:
•
Batteries are disconnected from the system bus.
•
The ac source circuit breakers are turned OFF.
•
The system ac and dc load circuit breakers/fuses are OFF or
removed.
Rectifier
Installation
Notes
Install rectifiers from bottom to top of cabinets. Vacant rectifier
position below or beside the top installed rectifier in a cabinet may
cause over-heating of the installed rectifiers. Install a Rectifier Shelf
Cover / Air Dam into vacant positions.
Install Rectifier Shelf Cover / Air Dam on rectifier shelves as
required. See Figure 15-4.
When installing a single 595LTA or 595LTB on a shelf, install an
Air Dam to block vacant right or left rectifier position.
Rectifier Shelf Cover Covers both left and right rectifier positions
(848680211)
Air Dam
Covers the left or right rectifier position
(848754358)
Continued on next page.