When a probe is in a furnace, soot will collect in the end of the probe, which will have a
negative effect on the performance of the probe. Burnoffs are used to clean out the built-up
carbon by burning it off of the probe.
Burnoff:
Clicking on this value allows users to manually initiate burnoff procedure. The user will have to
confirm this action
Configurator – Confirm burnoff
The “Test Status” will show that a burnoff is in progress.
Impedance Test:
Clicking on this value manually turns on/off the impedance test (this can
only
be initiated
manually). This test lasts 30 seconds. The user will have to confirm the action.
Configurator – Confirm impedance test
The “Test Status” will then become “Impedance Test”.
Cancel:
Clicking on this value will manually turn off both the burnoff and the impedance test. The user
will have to confirm this action.
Configurator – Confirm cancellation
Next Burnoff: (shown in minutes):
This value is a displayed calculation based on the burnoff time set in the
Probe Burnoff Setup
menu option. It displays the number of minutes until the next burnoff will be initiated.
Test Status:
This value displays the current testing status. The list of possible values are: Burnoff, Burnoff
Recovery, Idle, Impedance Recovery, or Impedance
Timer: