beautypg.com

Rockwell Automation 7000 PowerFlex Medium Voltage AC Drive (B Frame) - Classic Control User Manual

Page 338

background image

6-48

Component Definition and Maintenance

7000-UM150I-EN-P – June 2013

7000 “B” Frame

Equipment needed:


• Digital oscilloscope

• Function generator w/duty cycle control

• DC power supply (+15V @ 300 mA required)

• Digital multimeter

• Temperature sensor board (80190-639-02)

Procedure:

1. Connect a clamped ABB #5STP03D6500 SCR to the gate-cathode

leads of the SPGDB board (TB4-1/TB4-2).

2. Attach a temperature sensor board to the TB2-1/TB2-2 terminals.

3. Apply +15V test power to terminals TB3-1 and TB3-3 (TB3-1 is

at +15V while TB3-3 is the +15V return). Leave TB3-2 open.

4. Measure TP4 to TP3, which should be +14.4V, +/-100mV.

5. Measure TP5 to TP3, which should be +5.0V, +/- 250mV.

6. Measure TB2-1 to TB2-2, which should be +14.4V, +/-100mV.

7. Measure the voltage at U4-pin2 to COM, which should be

+1.0V, +/- 100mV.

8. Measure the voltage at U4-pin3 to COM, which should be 0V.

9. Measure the voltage at U4-pin7 to COM, which should be

+3.6V, +/- 100mV.

10. Verify that the OT1 LED is off.

11. Measure TP7 to TP3, which should be 0V.

12. Measure TP9 to TP3, which should be +5.0V, +/- 250mV.

13. Measure TP8 to TP3, which should be 0V.

14. Measure TP1 to TP2, which should be 0V.

15. Connect a jumper between TB3-1 and TB3-2 and verify that the

voltage at TP6 is +2.2V, +/-100mV.

16. Apply a 60Hz, 33% duty cycle signal to the OP1 fiber optic input.

17. Verify that the diagnostics transmitter LED, OT1, is on.

18. Verify that the signals at TP9 and TP8 are as shown in Fig. 6.34.

19. Verify that the signal between TP1 and TP2 is as shown in

Figures 6.35 and 6.36.

20. Remove the jumper between TB3-1 and TB3-2.

21. Apply a constant fiber optic signal to the OP1 input.

22. Apply a 60 Hz, 33% duty cycle signal, at a 0 to +2V level,

between the TB1-2 input and COM. Verify the signals in
Figures 6.37 and 6.38. Note that in Figure 6.38 there should be a
220 µS, +/-20 µS time between the rising edge of the U4-pin7
pulse and the falling edge of the TP7 signal.

Testing procedure for

SCR self-powered gate

driver board