Hydraulic installation checklist, Final hardware installation checklist, Geosteer performance checklist – Ag Leader GeoSteer Installation Manual User Manual
Page 58

Overview
48
GeoSteer System
Hydraulic Installation Checklist
1. Steering Valve Bracket and Steering Valve installed and all fasteners are tight.
2. All hose fittings are tight.
3. Checked for oil leaks on all hydraulic connections.
4. All hoses routed and secured with cable ties.
5. Stand by pump pressure has been measured.
Value __________
6. Maximum pump pressure has been measured.
Value __________
7. Load Sense Pressure Relief Valve has been adjusted and locked.
Value __________
8. Manual Steering is normal after the GeoSteer installation.
Final Hardware Installation Checklist
1. Assisted Steering Unit installed and all fasteners and brackets are tight.
2. Wheel Angle Sensor installed and all fasteners and rods are tight.
3. Display Bracket and Display installed and all fasteners are tight.
4. GeoDock is installed.
5. GeoSteer Control Unit is installed firmly to frame and all fasteners are tight.
6. All cable ends and terminations are connected.
7. All cables are secured with cable ties.
GeoSteer Performance Checklist
1. Verified manual steering speed from lock to lock is satisfactory.
Value __________ Sec
2. Verified GeoSteer steering speed from lock to lock is satisfactory.
Value __________ Sec
3. Checked the total Wheel Angle Sensor Counts.
Left
__________
Center
__________
Right
__________
4. Verified that manual kick-out is working when turn the steering wheel.
Value __________
5. Completed the GeoSteer system calibration.
6. Completed the GeoSteer system tuning (if necessary).
7. Verified Line acquisition performance is satisfactory.
8. Verified On-line steering performance is satisfactory.
Not
Applicable
Completed