beautypg.com

Commissioning, Hart, Hart) – Burkert Type 8635 User Manual

Page 125: Preparation

background image

8635 - 123

O

PERATING VIA THE

HART

HAND TERMINAL

(HART)

Commissioning

Preparation

Before commissioning, execute the fluidic and electrical installations.

Connect the HART hand terminal via the 2-pole communication line to the SIDE Control. Attach the
communication lines parallel to the setpoint standard signal. Correct polarity must not be observed.

Supply the SIDE Control with pneumatic auxiliary energy (inlet air) and apply a setpoint

≥ 4 mA.

Switch on the hand terminal with the

I/O key: the display shows for a few seconds a self-test

message. If the hand terminal was connected for the first time to the field device, a warm start is
executed which is completed with the function key

F3 - NEXT. In the display appears the basic menu

for the SIDE Control Type 8635 in the on-line mode.

On first commissioning, execution of the

Autotune function is absolutely necessary. SIDE Control

automatically determines the optimum settings for the current operating conditions (see also the
chapter

Operating and Controller Functions).

The menu item

AUTOTUNE is to be found in the Main menu under item 2.

AUTOTUNE

procedure (required on first commissioning)

Select the menu item

AUTOTUNE in the Main menu via the operating keys or and then start the

function via the operating key

. The following message appears.

Message after start of

the

AUTOTUNE function.

Warning before start of

AUTOTUNE function.

With

F3 - ABORT you can quit the AUTOTUNE function without starting.

With

F4 - OK you confirm the start.

After pressing the

F4 key, a warning message appears that the AUTOTUNE function may cause

malfunctions in the running process.