beautypg.com

Selecting advanced or basic verify schedules, Removing a task slot from a schedule – Avago Technologies 3ware 9650SE-12ML (Channel) User Manual

Page 188

background image

Maintaining Units

176

3ware SAS/SATA RAID Software User Guide, Version 9.5.1

2

In the Schedule Rebuild Tasks section, select the appropriate setting:

Follow Schedule

or

Ignore Schedule

.

The illustration below shows this setting for the rebuild task schedule.

Selecting Advanced or Basic Verify Schedules

You cannot ignore a verify schedule. You can only select either Basic or
Advanced as the verify schedule.

The Basic verify schedule is selected by default and is scheduled to run once a
week at Friday 12 am. You can change the time at which it runs on the
Schedule page in 3DM or on the Policy screen in 3BM.

The Advanced verify schedule is similar to the Rebuild/Migrate schedule and
has seven scheduling slots. For details about the functioning of Basic and
Advanced verify schedules, see “Using Auto Verification” on page 164.

To select Basic or Advanced verify schedule

1

Choose

Management > Schedule

from the menu bar.

The Scheduling page appears, showing the schedule for Rebuild/Migrate
Tasks.

2

From the drop-down menu, select

Verify Tasks

.

The Schedule Verify Tasks page appears.

3

Select either

Basic

or

Advanced

as the verify schedule.

Removing a Task Slot from a Schedule

By default, seven daily task schedule slots are defined, each starting at 12:00
am and running for 24 hours.

A maximum of seven schedule slots can be defined. When seven schedule
slots are shown for any of the tasks, you must remove a schedule slot before
you can add another.

Note:

Self-test schedules cannot be turned off in this way. To disable self-tests you

must either remove all schedule times, or uncheck the tests listed in the

Tasks

column. For more information, see “Selecting Self-tests to be Performed” on
page 178

.